Jokioisten Museorautatie

Select your language

vaihde-1

Two important turnouts of track number 1 of Minkiö yard will be fully rebuilt in winter 2009-2010. In the weekend 24.-25.10 the turnouts were removed in elements with the help of an excavator and piled next to a road. Today 3.11. the elements were picked up by a truck and taken to a shop for a complete rebuild. The points, frogs and the mechanism will be rebuilt and new cross ties installed. The renovated turnouts will be put back in their place in spring 2010. This work is part of the Minkiö yard rebuilding which started in 2006.